Hyperscale Data Center Build-Out

Salas O’Brien assisted a client in fast-tracking the construction of a multi-phased 350MW hyperscale data center with advanced electrical and cooling systems. The data center has complete electrical systems with N+1 reliability, from the utility to individual connections. In addition, our site planning services included a private substation. The facility can accommodate future on-site utility-scale battery generation. It features an 82,000-ton chilled water plant that uses high-efficiency centrifugal water-cooled chillers, open-circuit cooling towers, and plate and frame heat exchangers for waterside economizing and thermal energy storage. The chilled water plant operates in economizer mode for a larger portion of the year using an elevated chilled water temperature. Local officials fast-tracked design team progress submissions via an over-the-shoulder review process for temporary construction permits within weeks of project kickoff. Our rapid design allowed all equipment to be ordered and drawings to be approved before a permit was issued, which allowed the phase 1 data center to be energized within ten weeks of project kickoff.

COMPLETION YEAR

2025

SIZE

850,000 square feet

Features

350 MW
Total Capacity
225k
GPU Cluster
13 MGD
Water Recycling plant